Case Study

Project Wolverhamptom

Project: Stabilisation of existing stone wall
Location: Penn / Wolverhampton
Contract Duration: 14 Days
Anchors Installed 400
Area Treated: 500m2

 

Stabilisation of an existing 200 year old stone wall adjacent to a public road

The aim of this project was to support an existing stone wall which was collapsing, with debris spilling into the adjacent road. The road had to be closed for safety and temporary supports had been placed to provide short term support. These supports were adjusted as the works progressed to facilitate installation of the soil nails.

Once the nails were installed mini piles were drilled to provide a footing and a new wall constructed in front of the existing. The soil nails were also extended through the new wall to tie both walls together.

The overall length of the wall was 250m with a height of 2m, a total of 400 No. 6m long soil nails were installed in 2 rows.

Ask for a similar project

 

  • 1.jpg
  • 2.jpg
  • 3.jpg
  • 20150225_100623.jpg
  • 20150226_090902.jpg
  • 20150226_090906.jpg

Choose us for reliability

No matter if its a big complicated project or a small basic project, we aim to ensure your project is completed both ontime and on budget.


Known for innovation

With our vast experience in this area we can find a solution for your project no matter how difficult or challanging your project may be.

Select us for quality

With over 50 years combined experience in this industry, be rest assured your project will be completed professionally and the the highest standards.


Contact us for more info...

For more information or to discuss your project, please dont hesitate to contact us and we will be happy to discuss your requirements.

View Services or Get Free Quote