Project Solihull

Project: Soil nails &mini gabion mattress
Location: Solihull
Contract Duration: 20 Days
Area Treated: 655m2

 

The construction of a soil nail stabilised steep slope was concluded to be the most cost effective approach to provide much needed additional storage facilities for a major UK car manufacture. Excavating into the toe of an existing slope a 70 degree steep slope with a maximum height of some 8.0metres above adjacent hard standing level and some 100.0metres total length was formed.

Working with the Main Contractor, Intec Project Solutions Ltd and JTS Geotechnical Solutions Ltd provided the design and installation of the soil nails and integral stone filled heavy duty gabion mattress facing as preferred by the client.

Installation utilises a top down construction technique where soil nailing and associated facing elements stabilises the 70 degree face as excavation proceeds layer by layer. The soil nail stabilised steep slope including facing was completed within 20 days.

Ask for a similar project

 

  • Before Job Start.jpg
  • Completed 1.jpg
  • Completed.jpg
  • DAY 1.jpg
  • DAY 3.jpg
  • DAY 5.jpg
  • DAY 7.jpg
  • DAY 8.jpg
  • DAY 9.jpg
  • DAY 16.jpg
  • DAY 20.jpg
  • DAY 22.jpg

Choose us for reliability

No matter if its a big complicated project or a small basic project, we aim to ensure your project is completed both ontime and on budget.


Known for innovation

With our vast experience in this area we can find a solution for your project no matter how difficult or challanging your project may be.

Select us for quality

With over 50 years combined experience in this industry, be rest assured your project will be completed professionally and the the highest standards.


Contact us for more info...

For more information or to discuss your project, please dont hesitate to contact us and we will be happy to discuss your requirements.

View Services or Get Free Quote