Project: |
Soil Nailing & Mini Gabions |
Location: |
Kent |
Contract Duration: |
5 Days |
Soil Nails Installed: |
58 |
Area Treated: |
110m2 |
Replacement Failed retaining wall
JTS undertook a project in Northfleet, Kent and the logistics of the scheme were very complex due to the limited access. Section 1 at the rear of the building was the trickiest part of the project only accessible via three sections of steep stairways. The work consisted of removing the existing failed retaining wall and installing soil nails and completing with a mini gabion facing.